When we were there on Saturday, there was a big mud splatter on the bedroom wall that we were going to ask about. But by the Monday the brick cleaner had been through and done his thing (by all accounts he was very happy with the brick layer)... one less thing to bug the SS about.
I was right, the bricks were to fill in the gable (pictured above), 400 is the minimum order. I don't think they forgot so much as changed the standards, but either way I'm happy, bricks all the way up and plenty left over for a letterbox.
The plasterers finished on Monday, Wednesday and Thursday saw the carpenters come and start their work. Not sure when the brickie returned to do the gable, but it was done by Saturday. Here's the progress in pictures:
(Click image for larger view)
The shower has it's vilaboard... as far as I know it's still waiting for the waterproofing. The downpipes should be happening shortly too.
So does the door to the en-suite - and to the left you can see they also started the skirting boards.
We also have the external door to the en-suite! (Don't worry we plan to put some sort of frosting / curtain on it!)
We also have an internal access door from the garage... they had fully plastered over it for lock-up stage! 8-)
All in all, we are very happy with the progress.
Carpentry continues for another week or so, then painting and tiles, little by little every day...